Mine Shift Production Pace Calculator
Compare shift tonnes achieved with target and calculate the average rate needed during remaining hours.
Mine Shift Production Pace Calculator
FREE ONLINE TOOLWHEN IT HELPS
Common uses
- Check the worked example: With a 500 t target, 320 t achieved and 4 hours left, 180 t remain at 45 t/h.
IN PRACTICE
Example
With a 500 t target, 320 t achieved and 4 hours left, 180 t remain at 45 t/h.
GOOD TO KNOW
Does the required rate guarantee the target?
No. It is a pace comparison from the entered figures, not a forecast. Breaks, availability, material quality and operating constraints can change output.
Achievement = actual / target × 100; required remaining rate = max(0, target − actual) / remaining hours. No. It is a pace comparison from the entered figures, not a forecast. Breaks, availability, material quality and operating constraints can change output.
Frequently asked questions
Does the required rate guarantee the target?
No. It is a pace comparison from the entered figures, not a forecast. Breaks, availability, material quality and operating constraints can change output.
Which formula is used?
Achievement = actual / target × 100; required remaining rate = max(0, target − actual) / remaining hours.